Installation day: what happens and what we need from you

What our technician does, what access they need and what you should have ready.

What we install

  • The Sync Energy 7.4kW socket chargepoint at your parking space
  • The cabling from our electricity supply to your space
  • If we haven’t already installed the communal infrastructure in your carpark, then we’ll install the cabinet, circuit breakers and the connection to the meter

What you need to provide

🔌

Your charger has a socket rather than a fixed cable, so you will need your own Type 2 charging cable. We recommend a 32A cable to get the full 7.4kW. A 16A cable will work but will charge more slowly.

Access our technician needs

On the day, they will need to get to:

  • The meter room, or wherever the meter in Tohmo's name is located
  • Our cabinet
  • The common areas the cabling runs through
  • Your parking space itself

If your car park needs a fob, a key or a code, please make sure that is arranged in advance. If a vehicle or anything else is blocking your space, it needs to be moved before the technician arrives. Moving vehicles or furniture is not something they can do on your behalf.

Do you need to be there?

No, you do not need to be on-site when your chargepoint is being installed. If we need your bay to be clear of any vehicles, we will notify you in advance.

After the work is finished

Your chargepoint is tested and commissioned, and the work is recorded in a report confirming the exact date of connection and what was done. That date is your Connection Date, and it is when your subscription starts.