From signing to first charge: your installation timeline

What happens after you sign, when your date is confirmed and what can affect the timing.

Step-by-step

Before you sign: your quote and OZEV application

If you are purchasing your own charger for an underground car park and applying for the OZEV grant, we will first provide a quote for you to use in your application. We can only move on to your Subscription Contract once your OZEV application has been approved.

  1. You sign your Subscription Contract
    1. Signed electronically, along with your bank details for payment.

  1. We confirm your installation date, usually within 10 days
    1. We agree the date directly with you rather than allocating one.

  1. Your charger is installed, typically within around six weeks of signing
    1. Most installations take a few hours.

  1. Your charger is commissioned and tested
    1. The date this happens is your Connection Date, and it is recorded in an installation report.

  1. Your subscription and billing begin
    1. Nothing is charged before this point.

What can affect the timing

A few things sit outside our direct control:

  • Building approvals. If your freeholder or managing agent has not yet signed a Building Agreement, we need that in place first.
  • OZEV application processing. If you are applying for the grant, the time OZEV takes to review and approve your application can affect your installation timeline. We can only move on to your Subscription Contract once approval is confirmed.
  • The electricity network. Some work depends on the local Distribution Network Operator. Where they set the pace, we cannot speed it up, though we will keep you posted.

If your installation is going to take longer than expected, we would rather tell you early than let the date drift quietly. Get in touch any time at uk@go-tohmo.com for an update.